Planning application approved: camp site, Wellsyke Lane

The Parish Council has been notified that the recent planning application to resurface existing roads at THE CAMPING AND CARAVANNING CLUB, WELLSYKE LANE, KIRKBY ON BAIN, WOODHALL SPA, LN10 6YU was approved yesterday. The ELDC reference number is S/094/02458/18

To view the application online visit the ELDC website using this link.

Continue reading

Advertisements

Road closures: Kirkby Lane and Woodhall Spa

Roads in Woodhall Spa and part of Kirkby Lane are scheduled for temporary closure:

The works are expected to last for six weeks, subject to suitable weather. The first week of works, from Monday 22 October to Friday 26 October, will be carried out under temporary traffic signals from 8am to 8pm.

The remainder of the project, which includes approximately four days of resurfacing works on Kirkby Lane and approximately two days of resurfacing on Iddesleigh Road, will be carried out under a full road closure of the B1191 and Kirkby Lane from 8am to 8pm, Monday to Friday.

Temporary two-way traffic signals will also be in use from 10am to 6pm to allow works to be carried out on the following Saturdays: 27 October, 3 November, 10 November and 17 November. Full details here Continue reading

Road works in Horncastle

Major road works in Horncastle started yesterday, involving carriageway resurfacing, junction and traffic signal improvements in the town centre and the construction of a new shared footway/cycle pathway on Langton Hill.

Phase 1: West Street to be reconstructed from the junction with Reindeer Close to the Bridge Street/Prospect Street junction. Works are scheduled to end by September 10th.

Changes to bus services until the end October: Continue reading