Road closures: Kirkby Lane and Woodhall Spa

Roads in Woodhall Spa and part of Kirkby Lane are scheduled for temporary closure:

The works are expected to last for six weeks, subject to suitable weather. The first week of works, from Monday 22 October to Friday 26 October, will be carried out under temporary traffic signals from 8am to 8pm.

The remainder of the project, which includes approximately four days of resurfacing works on Kirkby Lane and approximately two days of resurfacing on Iddesleigh Road, will be carried out under a full road closure of the B1191 and Kirkby Lane from 8am to 8pm, Monday to Friday.

Temporary two-way traffic signals will also be in use from 10am to 6pm to allow works to be carried out on the following Saturdays: 27 October, 3 November, 10 November and 17 November. Full details here

 

 

 

 

 

 

 

 

If you have any queries, or require further information, please contact the LCC Customer Service Centre on 01522 782070.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.